PORTLAND, Maine (AP) — A battle over a $1 billion transmission line that won all regulatory approvals only to be rebuked by state residents in a referendum now comes down to nine regular folks.

In a rare move, a jury is being asked to decide a complicated constitutional matter — whether developers have a vested right to complete the 145-mile (233-kilometer) project, which would supply Canadian hydropower to the New England power grid.

The constitutionality of the statewide referendum on the project depends on the jury’s decision on the narrow vested-rights issue. And the case could turn on a simple majority of jurors.

“We’re not aware of a similar instance in which the fate of a large energy asset rests in the hands of a jury. This is an unusual circumstance,” Timothy Fox, vice president of Clear View Partners, an energy research firm in Washington, D.C., said before the trial began Monday.

The courtroom was packed Monday.

Attorneys for groups opposed to the project and the state attorney general’s office, which is charged with upholding the referendum, suggested to jurors on Monday that developers rushed construction with a goal of winning vested rights and nullifying the referendum.

But John Armando, lawyer for the developers, said the construction schedule was put in place years earlier, and that the case is “about fundamental fairness, about vested rights, about protection of property rights against retroactive laws.”

Last year, the Maine Supreme Judicial Court substantial construction already had begun in good faith before the referendum. Construction started in January 2021, about 10 months before the referendum in which 59% of voters rejected the project.

Justice Michael A. Duddy could have made the fact-finding determination himself but ruled in favor of project opponents, including the Natural Resources Council of Maine, who asked for a jury to make the determination. That ruling is considered a victory for those who are opposed to the project.

Central Maine Power’s parent company and Hydro Quebec teamed up on New England Clean Energy Connect, which was unveiled in 2017 with a goal of supplying up to 1,200 megawatts of Canadian hydropower to the New England power grid. That is enough electricity for 1 million homes.

It’s one of two proposed large-scale transmission projects aimed at tapping hydropower from Quebec. The other would provide electricity to New York City.

Early on, developers envisioned smooth sailing because the transmission path would mostly follow existing corridors, with only a new 53-mile (85-kilometer) section crossing sparely populated woods to reach the Canadian border.

But the project encountered opposition each step of the way even as it received all necessary regulatory approvals. Developers already had begun cutting trees and setting poles for months when the governor asked for work to be suspended after voters rejected the project in November 2021.

Supporters say bold projects such as this one, funded by ratepayers in Massachusetts, are necessary to battle climate change and introduce additional electricity into a region that is heavily reliant on natural gas, which can cause spikes in energy costs.

Critics say the project’s environmental benefits are overstated — and that it would harm the woodlands in western Maine.

In Maine, two lawsuits over the project went before the Supreme Judicial Court, which ultimately upheld a lease for a 1-mile portion of the proposed power line that crossed state land.

The constitutional issue will likely end up back before the Supreme Judicial Court regardless of the outcome of the judge’s decision after the jury trial.

___

Follow David Sharp on Twitter @David_Sharp_AP

United States News

Associated Press

Google plans to invest $2 billion to build data center in northeast Indiana, officials say

FORT WAYNE, Ind. (AP) — Google plans to invest $2 billion to build a data center in northeastern Indiana that will help power its artificial intelligence technology and cloud business, company and state officials said Friday. The data center planned for Fort Wayne was announced in January. But Google disclosed the project’s cost Friday and […]

13 minutes ago

Associated Press

Ex-Nebraska deputy is indicted in connection with fatal highway shooting

SEWARD, Neb. (AP) — A former Nebraska deputy is jailed after a grand jury indicted him on suspicion of manslaughter in connection with the shooting death of a man in October, a prosecutor said Friday. Lancaster County Attorney Pat Condon announced the indictment of former Seward County Deputy Anthony Gann. Gann is jailed on $100,000 […]

16 minutes ago

Associated Press

The Latest | Trump prosecutors claw back at defense’s portrait of tabloid deal

NEW YORK (AP) — Defense lawyers in Donald Trump’s hush money trial dug Friday into assertions of the former publisher of the National Enquirer and his efforts to protect Trump from negative stories during the 2016 election. David Pecker returned to the witness stand for the fourth day as defense attorneys tried to poke holes […]

8 hours ago

Associated Press

As some universities negotiate with pro-Palestinian protesters, others quickly call the police

The students at Columbia University who inspired pro-Palestinian demonstrations across the country dug in at their encampment for the 10th day Friday as administrators and police at campuses from California to Massachusetts wrestled with how to address protests that have seen scuffles with police and hundreds of arrests. Officials at Columbia and some other schools […]

14 hours ago

Associated Press

Trump’s lawyers grill ex-tabloid publisher as 1st week of hush money trial testimony nears a close

NEW YORK (AP) — After prosecutors’ lead witness painted a tawdry portrait of “catch-and-kill” tabloid schemes, defense lawyers in Donald Trump’s criminal trial on Friday sought to dig into an account of the former publisher of the National Enquirer and his efforts to protect Trump from negative stories during the 2016 election. David Pecker returned […]

15 hours ago

Harvey Weinstein’s 2020 rape conviction is overturned by New York court....

Associated Press

Harvey Weinstein’s rape conviction is overturned by New York’s top court

Harvey Weinstein’s 2020 rape conviction is overturned by New York court with Weinstein remaining in prison.

17 hours ago

Sponsored Articles

...

Condor Airlines

Condor Airlines can get you smoothly from Phoenix to Frankfurt on new A330-900neo airplane

Adventure Awaits! And there's no better way to experience the vacation of your dreams than traveling with Condor Airlines.

...

Collins Comfort Masters

Here’s 1 way to ensure your family is drinking safe water

Water is maybe one of the most important resources in our lives, and especially if you have kids, you want them to have access to safe water.

...

Collins Comfort Masters

Avoid a potential emergency and get your home’s heating and furnace safety checked

With the weather getting colder throughout the Valley, the best time to make sure your heating is all up to date is now. 

Jury holds key to fate of $1 billion transmission project