AG Kris Mayes asks Cochise County to delay vote on SpaceX data center
The proposed campus near Willcox would use about 6 gigawatts of electricity, nearly 20% of Arizona’s power-generating capacity. Mayes says questions about power, water and fire safety remain unanswered.
Watch: Is Elon Musk actually putting AI chips in space? | 53 seconds
Arizona Attorney General Kris Mayes on Thursday asked Cochise County officials to delay a vote on a huge SpaceX data center proposed in rural southeastern Arizona.
In a letter to the county Planning and Zoning Commission, Mayes said the panel should wait until state and federal agencies finish reviewing the project. The commission is set to vote Dec. 9.
“The people of Cochise County deserve answers before county officials approve a project of this magnitude,” Mayes said.
Her letter says the company has not explained where most of the campus’ power would come from, how much water it would take to make that electricity in an area already short on groundwater, or whether rural firefighters could handle a fire among thousands of large batteries. She also cited traffic, wildlife and military testing nearby.
What SpaceX wants to build in Cochise County
SpaceX, through a company called Tombstone Resources LLC, wants to build up to nine computing buildings on about 747 acres along U.S. Highway 191 near the town of Cochise.
When finished, the campus would draw about 6 gigawatts of electricity, nearly 20% of all the power Arizona can generate, according to Mayes.
That’s close to 1.5 times what the Palo Verde nuclear plant west of Phoenix, the country’s biggest power producer, can put out.
It’s also enough to keep the lights on in roughly 1 million Arizona homes, based on a utility estimate.
Mayes, who called for a statewide pause on new data centers, said any permit should not take effect until the project has every state and federal approval it needs.
Mayes’ office will hold its own town hall Dec. 3 at Cochise Elementary School.