Phoenix wastewater plant is flush with upgrades after $73.5M rehab
Design is already underway on the next section of the 91st Avenue Wastewater Treatment Plant to be rebuilt.
Watch: Water Watch: How a Valley wastewater treatment plant cools nuclear plant, feeds Salt River | 1 min
A $73.5 million overhaul of one of eight treatment lines at the Valley’s largest wastewater plant is finished, and city officials say more work is on the way.
The rehabilitation of Plant 2B at the 91st Avenue Wastewater Treatment Plant in Tolleson began in June 2023 and was completed in September 2026.
Crews replaced aging pumps, piping, electrical systems and basin equipment. They swapped a chemical odor scrubber for an in-ground biofilter.
“I don’t believe we’ve ever done a full rehab on that plant,” Phoenix Assistant Water Services Director Nazario Prieto told KTAR News 92.3 FM. “Wastewater is extremely harsh on infrastructure.”
The facility can treat about 230 million gallons a day, and Plant 2B handles about 36 million of that. Ratepayers in Phoenix, Glendale, Mesa, Scottsdale and Tempe, the five cities that share the facility, covered the improvement cost.
More Phoenix wastewater upgrades on the way
Design is underway on Plant 1A, the next treatment line due for a rehab.
“We’re just going to continue going through one plant at a time until we get through all of them,” Prieto said.
The upgrades also prepare the plant for Pure Water Phoenix, the city’s plan to purify treated wastewater into drinking water.
“It’s imperative that our wastewater treatment facility is in the best shape it can be,” Prieto said.
KTAR News 92.3 FM’s Heidi Hommel contributed to this report.