Flyover bridge taking shape at new US 93-Interstate 40 interchange in Kingman

The $106 million project connecting Interstate 40 and US 93 is 85% complete and scheduled to open in spring 2027.

Kingman flyover to ease traffic on Phoenix-to-Las Vegas route...

(Photo via Arizona Department of Transportation)

(Photo via Arizona Department of Transportation)

A flyover bridge that will carry Las Vegas-to-Phoenix traffic through Kingman is taking shape, with crews installing its final girders at the new US 93-I-40 interchange.

The milestone brings the $106 million project to 85% completion as the Arizona Department of Transportation works toward fully opening the interchange in spring 2027.

The bridge will connect southbound US 93 with eastbound I-40, allowing drivers traveling toward the Valley to avoid the traffic signal at Beale Street. It’s part of a broader effort to ease delays along the main highway route between Phoenix and Las Vegas.

For now, travelers should continue to expect lane restrictions during daytime and overnight construction. Beale Street exits on both highways remain accessible for trips to local businesses, Route 66 and downtown Kingman.

What’s next for the Kingman flyover bridge?

With the final support beams in place, crews will turn to pouring the bridge’s concrete deck in December.

The approximately 1,100-foot-long structure curves over westbound I-40 at Clack Canyon. The latest work involved lifting 10 girders into position across two spans, each roughly 160 feet long.


Subscribe to the KTAR Daily Connect newsletter to get our top news stories, exclusive guest interviews and more to your email inbox.


Elsewhere on the project, workers are paving the mile-long ramps that will connect the highways and widening I-40’s White Cliffs bridges. Those bridge widenings are also 85% finished.

The latest progress follows the September opening of a 239-foot tunnel, another piece of the interchange that is already serving drivers. It is the project’s second tunnel and is expected to handle more traffic than the first.

What else does the project include?

The finished interchange will encompass 6 miles of new or widened roadway, including a mile of highway northwest of the existing connection at I-40 and Beale Street.

Plans also call for a wider stretch of I-40 between the new interchange and Stockton Hill Road, an additional merge lane on northbound US 93 and drainage improvements.

In all, the construction includes four new bridges, two bridge widenings, four bridge rehabilitations and 2 miles of sound walls.

ADOT began work on the project in July 2024.

Get the latest KTAR News 92.3 FM traffic alerts sent straight to your phone by texting “TRAFFIC” to 620620.

Serena O'Sullivan KTAR News Reporter and Editor

Serena O’Sullivan is a Phoenix-based news reporter and content editor for KTAR.com, where she covers local and national stories with a digital-first approach. Her reporting has appeared in major outlets including USA Today, Arizona Republic, Phoenix… Read more

Comments

0 Comments