AP

US nuclear agency falls short on scheduling, cost estimates

Jan 12, 2023, 3:46 PM | Updated: 11:16 pm

FILE - In this Nov. 20, 2013 file photo, seen through thick protective glass, shows the area where ...

FILE - In this Nov. 20, 2013 file photo, seen through thick protective glass, shows the area where workers sand-blast the large stainless steel tanks used in the vitrification process to rid them of contaminants at the Defense Waste Processing Facility at the Savannah River Site near Aiken, S.C. The U.S. agency in charge of jumpstarting the production of key components for the nation's nuclear arsenal is falling short when it comes to having a comprehensive schedule for the multibillion-dollar project. The Government Accountability Office said in a report released Thursday, Jan. 12, 2023, that plans by the National Nuclear Security Administration for reestablishing plutonium pit production do not follow best practices and run the risk of delays and cost overruns. (AP Photo/Stephen B. Morton,File)

(AP Photo/Stephen B. Morton,File)

ALBUQUERQUE, N.M. (AP) — The U.S. agency in charge of jumpstarting the production of key components for the nation’s nuclear arsenal is falling short when it comes to having a comprehensive schedule for the multibillion-dollar project.

The Government Accountability Office said in a report released Thursday that plans by the National Nuclear Security Administration for reestablishing plutonium pit production do not follow best practices and run the risk of delays and cost overruns.

The federal government has not manufactured plutonium cores regularly in more than 30 years and faces a congressionally mandated deadline of turning out at least 80 per year by 2030.

The GAO describes the modernization effort as the agency’s largest investment in weapons production infrastructure to date, noting that plutonium is a dangerous material and making the weapon cores is difficult and time consuming.

“NNSA lacks both a comprehensive cost estimate and a schedule outlining all activities it needs to achieve this capability,” the reports states.

Nuclear watchdog groups have been voicing similar concerns since the federal government first announced plans in 2018 to restart production by splitting the work between Los Alamos National Laboratory in northern New Mexico and the Savannah River Site in South Carolina.

At stake are billions of dollars in funding for improving infrastructure at the two locations and thousands of jobs.

Democratic members of New Mexico’s congressional delegation have fought to ensure Los Alamos — a once secret city that helped develop the atomic bomb as part of the Manhattan Project — would be among the benefactors of the lucrative mission.

Using documents prepared by the nuclear agency for justifying its fiscal year 2023 budget, the GAO identified at least $18 billion to $24 billion in potential costs to build up production capacity.

However, the GAO, other independent analysts and officials in the U.S. Defense Department all have testified in recent years that NNSA would miss the 2030 deadline, no matter how much funding was funneled toward the project.

The NNSA said in a statement Thursday that it agreed with the GAO’s recommendations and that some of the work to implement best practices was underway.

“Both the lifecycle cost estimate data and (integrated master schedule) will be updated as needed to reflect the most up-to-date information as the projects and program work progress,” the agency said.

More specifically, the agency said in a letter to the GAO that it planned to complete the cost estimate for the overall project by September 2025 and that the schedule would “continue to mature over time.”

Greg Mello, director of the watchdog Los Alamos Study Group, said Thursday that not having a comprehensive schedule or cost estimate means NNSA does not know what it’s doing and has little likelihood of success.

“How can NNSA produce the required number of pits on schedule or on budget, when NNSA has no schedule or budget?” he asked. “These are elementary, normal components in any program or project. After more than two decades of preparation, NNSA doesn’t have them.”

Jay Coghlan, executive director of Nuclear Watch New Mexico, pointed to some of the price tags associated with the project having doubled over the last four years. He said production overall at the two sites could cost at least $60 billion over 30 years with radioactive waste disposal and other environmental and public health concerns adding to the bill.

Until Congress and the New Mexican delegation demand credible cost estimates and schedules, Coghlan said lawmakers “should stop rewarding the guilty with yet more money.”

“That is simple good governance that could help slow our sleepwalk into the new and unpredictable nuclear arms race,” he said.

Mello agreed, saying the mission needs to be widely debated in Congress, not just discussed behind closed doors or by those lawmakers who sit on defense committees.

In its report, the GAO outlined the process for making plutonium pits along with a history of how and where the work was done during the Cold War. The long-shuttered Rocky Flats Plant outside Denver was capable of producing more than 1,000 war reserve pits annually before work stopped in 1989 due to environmental and regulatory concerns.

With a long history of leaks, fires and other violations, Rocky Flats underwent a $7 billion cleanup that was finished in 2005.

During the Obama administration, a council made up of defense and energy officials told Congress the nation needed to produce between 50 and 80 pits per year. Congress included a legal mandate for production in a 2015 defense measure that was subsequently approved and signed by the president.

That mandate was later amended to call for the 80 pits in 2030. According to the GAO, some of the construction projects and upgrades needed for the work at Los Alamos won’t be finished for several years.

Copyright © The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

AP

Speaker of the House Mike Johnson, R-La., talks to reporters just after lawmakers pushed a $95 bill...

Associated Press

Ukraine, Israel aid advances in rare House vote as Democrats help Republicans push it forward

The House pushed ahead Friday on a foreign aid package of $95 billion for Ukraine, Israel, Taiwan and other sources of humanitarian support.

38 minutes ago

southern Arizona rancher George Alan Kelly...

Associated Press

Trial of a southern Arizona rancher charged in fatal shooting of unarmed migrant goes to the jury

Closing arguments were made against a southern Arizona rancher accused of shooting an undocumented migrant on his land to death on Thursday.

23 hours ago

Donald Trump's hush money trial: 12 jurors selected...

Associated Press

Although 12 jurors were picked for Donald Trump’s hush money trial, selection of alternates is ongoing

A jury of 12 people was seated Thursday in former President Donald Trump's hush money trial. The proceedings are close to opening statements.

1 day ago

A anti-abortion supporter stands outside the House chamber, Wednesday, April 17, 2024, at the Capit...

Associated Press

Democrats clear path to bring proposed repeal of Arizona’s near-total abortion ban to a vote

Democrats in the Arizona Senate cleared a path to bring a proposed repeal of the state’s near-total ban on abortions to a vote.

2 days ago

Most Americans are sleepy new Gallup poll finds...

Associated Press

Most Americans say they don’t get enough sleep, according to new Gallup poll

A new Gallup poll found that most Americans are sleepy — or, at least, they say they are. Multiple factors play into this.

4 days ago

Near-total abortion ban in Arizona dates back to Civil War era...

Associated Press

Near-total abortion ban dates back to 1864, during the Civil War, before Arizona was a state

The near-total abortion ban resurrected last week by the Arizona Supreme Court dates to 1864, when settlers were encroaching on tribal lands.

4 days ago

Sponsored Articles

...

DISC Desert Institute for Spine Care

Sciatica pain is treatable but surgery may be required

Sciatica pain is one of the most common ailments a person can face, and if not taken seriously, it could become one of the most harmful.

...

Collins Comfort Masters

Here’s 1 way to ensure your family is drinking safe water

Water is maybe one of the most important resources in our lives, and especially if you have kids, you want them to have access to safe water.

...

Collins Comfort Masters

Avoid a potential emergency and get your home’s heating and furnace safety checked

With the weather getting colder throughout the Valley, the best time to make sure your heating is all up to date is now. 

US nuclear agency falls short on scheduling, cost estimates