US nuclear agency falls short on scheduling, cost estimates

Jan 12, 2023, 3:46 PM | Updated: 11:16 pm

FILE - In this Nov. 20, 2013 file photo, seen through thick protective glass, shows the area where ...

FILE - In this Nov. 20, 2013 file photo, seen through thick protective glass, shows the area where workers sand-blast the large stainless steel tanks used in the vitrification process to rid them of contaminants at the Defense Waste Processing Facility at the Savannah River Site near Aiken, S.C. The U.S. agency in charge of jumpstarting the production of key components for the nation's nuclear arsenal is falling short when it comes to having a comprehensive schedule for the multibillion-dollar project. The Government Accountability Office said in a report released Thursday, Jan. 12, 2023, that plans by the National Nuclear Security Administration for reestablishing plutonium pit production do not follow best practices and run the risk of delays and cost overruns. (AP Photo/Stephen B. Morton,File)

(AP Photo/Stephen B. Morton,File)

ALBUQUERQUE, N.M. (AP) — The U.S. agency in charge of jumpstarting the production of key components for the nation’s nuclear arsenal is falling short when it comes to having a comprehensive schedule for the multibillion-dollar project.

The Government Accountability Office said in a report released Thursday that plans by the National Nuclear Security Administration for reestablishing plutonium pit production do not follow best practices and run the risk of delays and cost overruns.

The federal government has not manufactured plutonium cores regularly in more than 30 years and faces a congressionally mandated deadline of turning out at least 80 per year by 2030.

The GAO describes the modernization effort as the agency’s largest investment in weapons production infrastructure to date, noting that plutonium is a dangerous material and making the weapon cores is difficult and time consuming.

“NNSA lacks both a comprehensive cost estimate and a schedule outlining all activities it needs to achieve this capability,” the reports states.

Nuclear watchdog groups have been voicing similar concerns since the federal government first announced plans in 2018 to restart production by splitting the work between Los Alamos National Laboratory in northern New Mexico and the Savannah River Site in South Carolina.

At stake are billions of dollars in funding for improving infrastructure at the two locations and thousands of jobs.

Democratic members of New Mexico’s congressional delegation have fought to ensure Los Alamos — a once secret city that helped develop the atomic bomb as part of the Manhattan Project — would be among the benefactors of the lucrative mission.

Using documents prepared by the nuclear agency for justifying its fiscal year 2023 budget, the GAO identified at least $18 billion to $24 billion in potential costs to build up production capacity.

However, the GAO, other independent analysts and officials in the U.S. Defense Department all have testified in recent years that NNSA would miss the 2030 deadline, no matter how much funding was funneled toward the project.

The NNSA said in a statement Thursday that it agreed with the GAO’s recommendations and that some of the work to implement best practices was underway.

“Both the lifecycle cost estimate data and (integrated master schedule) will be updated as needed to reflect the most up-to-date information as the projects and program work progress,” the agency said.

More specifically, the agency said in a letter to the GAO that it planned to complete the cost estimate for the overall project by September 2025 and that the schedule would “continue to mature over time.”

Greg Mello, director of the watchdog Los Alamos Study Group, said Thursday that not having a comprehensive schedule or cost estimate means NNSA does not know what it’s doing and has little likelihood of success.

“How can NNSA produce the required number of pits on schedule or on budget, when NNSA has no schedule or budget?” he asked. “These are elementary, normal components in any program or project. After more than two decades of preparation, NNSA doesn’t have them.”

Jay Coghlan, executive director of Nuclear Watch New Mexico, pointed to some of the price tags associated with the project having doubled over the last four years. He said production overall at the two sites could cost at least $60 billion over 30 years with radioactive waste disposal and other environmental and public health concerns adding to the bill.

Until Congress and the New Mexican delegation demand credible cost estimates and schedules, Coghlan said lawmakers “should stop rewarding the guilty with yet more money.”

“That is simple good governance that could help slow our sleepwalk into the new and unpredictable nuclear arms race,” he said.

Mello agreed, saying the mission needs to be widely debated in Congress, not just discussed behind closed doors or by those lawmakers who sit on defense committees.

In its report, the GAO outlined the process for making plutonium pits along with a history of how and where the work was done during the Cold War. The long-shuttered Rocky Flats Plant outside Denver was capable of producing more than 1,000 war reserve pits annually before work stopped in 1989 due to environmental and regulatory concerns.

With a long history of leaks, fires and other violations, Rocky Flats underwent a $7 billion cleanup that was finished in 2005.

During the Obama administration, a council made up of defense and energy officials told Congress the nation needed to produce between 50 and 80 pits per year. Congress included a legal mandate for production in a 2015 defense measure that was subsequently approved and signed by the president.

That mandate was later amended to call for the 80 pits in 2030. According to the GAO, some of the construction projects and upgrades needed for the work at Los Alamos won’t be finished for several years.

Copyright © The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

AP

Republican presidential candidates, former New Jersey Gov. Chris Christie, left, talking with forme...

Associated Press

The GOP debate field was asked about Trump. But most of the stage’s attacks focused on Nikki Haley

The four Republican presidential candidates debating Wednesday night mostly targeted each other instead of Donald Trump.

3 hours ago

Law enforcement officers head into the University of Nevada, Las Vegas, campus after reports of an ...

Associated Press

Police say 3 dead, fourth wounded and shooter also dead in University of Nevada, Las Vegas attack

Police said a suspect was found dead Wednesday as officers responded to an active shooter and reports of multiple victims at UNLV.

5 hours ago

President Joe Biden's son, Hunter Biden, leaves after a court appearance, July 26, 2023, in Wilming...

Associated Press

Republicans threaten contempt proceedings if Hunter Biden refuses to appear for deposition

House Republicans are threatening to hold Hunter Biden in contempt if he does not show up this month for a closed-door deposition.

7 hours ago

Sen. Tommy Tuberville, R-Ala., listens to a question during a news conference, March 30, 2022, in W...

Associated Press

Tuberville is ending blockade of most military nominees, clearing way for hundreds to be approved

Sen. Tommy Tuberville announced Tuesday that he's ending his blockade of hundreds of military promotions, following heavy criticism.

1 day ago

An employee works inside the Hanwha Qcells Solar plant on Oct. 16, 2023, in Dalton, Ga. On Tuesday,...

Associated Press

US job openings fall to lowest level since March 2021 as labor market cools

U.S. employers posted 8.7 million job openings in October, the fewest since March 2021, in a sign that hiring is cooling.

1 day ago

Megyn Kelly poses at The Hollywood Reporter's 25th annual Women in Entertainment Breakfast, Dec. 7,...

Associated Press

The fourth GOP debate will be a key moment for the young NewsNation cable network

By airing the fourth Republican presidential debate, NewsNation network will almost certainly reach the largest audience in its history.

1 day ago

Sponsored Articles

(KTAR News Graphic)...

KTAR launches online holiday auction benefitting Boys & Girls Clubs of the Valley

KTAR is teaming up with The Boys & Girls Clubs of the Valley for a holiday auction benefitting thousands of Valley kids.

...

Dierdre Woodruff

Interest rates may have peaked. Should you buy a CD, high-yield savings account, or a fixed annuity?

Interest rates are the highest they’ve been in decades, and it looks like the Fed has paused hikes. This may be the best time to lock in rates for long-term, low-risk financial products like fixed annuities.

...

Desert Institute for Spine Care

Desert Institute for Spine Care (DISC) wants to help Valley residents address back, neck issues through awake spine surgery

As the weather begins to change, those with back issues can no longer rely on the dry heat to aid their backs. That's where DISC comes in.

US nuclear agency falls short on scheduling, cost estimates