RICHMOND, Va. (AP) — Dominion Energy has agreed to implement several consumer protections in connection with its massive offshore wind project under a proposed agreement with the office of the Virginia attorney general and other parties released Friday.

The proposed agreement, which includes performance reporting requirements and provisions laying out a degree of construction cost sharing, is still subject to final approval by the State Corporation Commission.

Attorney General Jason Miyares, a Republican whose office represents the interests of consumers in utility regulation proceedings, said the agreement would provide “first-of-its-kind” protections for ratepayers while ensuring the 176-turbine project with an estimated $9.8 billion capital cost moves forward in a fiscally responsible way.

“I am pleased that we have achieved consumer protections never seen before in modern Virginia history,” Miyares said in a statement. “For the first time Dominion has significant skin in the game to ensure that the project is delivered on budget. Should the project run materially over budget, it will come out of Dominion’s pocket, not consumers,” he said.

Dominion filed its application to build and recover the costs of the project with the State Corporation Commission nearly a year ago. That kicked off a lengthy process before the regulatory agency, one that has included voluminous filings and an evidentiary hearing in May.

The commission in August signed off on the project, but it included a consumer protection provision — a performance guarantee — that Dominion strenuously objected to, saying it would kill the project.

The parties to Friday’s proposal said they had conferred since then and reached the terms of the proposed agreement. It calls for a cost-sharing arrangement for any overruns beyond the estimated $9.8 billion price tag. The company would cover 50% of construction costs between the range of $10.3-$11.3 billion and 100% of costs between $11.3-$13.7 billion. If construction costs were to exceed $13.7 billion, the issue would go back to the commission.

The proposal would not require the company to guarantee certain energy production levels, like the SCC had initially ordered. Rather, Dominion will have to report average net capacity factors annually and “provide a detailed explanation of the factors contributing to any deficiency.” Capacity factor is a measure of how often a generating facility runs during a period of time.

Richmond-based Dominion said in a news release that the deal would provide “significant customer benefits.”

“I appreciate the thoughtful effort of all parties in reaching a constructive agreement to allow the project to continue moving forward,” said Bob Blue, Dominion’s chair, president and and chief executive officer.

Also parties to the agreement are Walmart, Virginia’s largest private employer, and two conservation groups: Appalachian Voices and the Southern Environmental Law Center.

Will Cleveland, an attorney for SELC, emphasized in a statement that the primary issue in the case was “never about offshore wind’s value but the risks created by the ownership structure.”

No other offshore wind project under development in the U.S. is funded by captive ratepayers, and no other project has a monopoly utility owner acting as its own general contractor, the law center said.

The project, which will be located about 27 miles off the coast of Virginia Beach, has drawn broad support from local officials, policymakers, business groups and trade unions, who say it will help fight climate change and create jobs.

The company already has a two-turbine pilot project up and running. The 2.6-gigawatt, utility-scale project’s schedule calls for construction to be complete in late 2026. Dominion expects the project to generate enough clean energy to power up to 660,000 homes.

Clean Virginia, an environmental and rate reform advocacy group that is a party to the proceeding, did not oppose the agreement, which it said in a statement represented a “vast improvement” for consumers.

“Absent pressure from environmental advocates, the Office of the Attorney General, regulatory staff, and Walmart, Dominion would have proceeded with one of the most expensive energy projects to date in Virginia with few consumer protections and would have faced little performance expectations to actually generate consistent clean energy,” Laura Gonzalez, the group’s energy policy manager, said in a statement.

Copyright © The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

AP

Lead water pipes pulled from underneath the street are seen in Newark, N.J., Oct. 21, 2021. (AP Pho...

Associated Press

Biden to require cities to replace harmful lead pipes within 10 years

The Biden administration has previously said it wants all of the nation's roughly 9 million lead pipes to be removed, and rapidly.

3 days ago

Facebook's Meta logo sign is seen at the company headquarters in Menlo Park, Calif., on, Oct. 28, 2...

Associated Press

Meta shuts down thousands of fake Facebook accounts that were primed to polarize voters ahead of 2024

Meta said it removed 4789 Facebook accounts in China that targeted the United States before next year’s election.

3 days ago

A demonstrator in Tel Aviv holds a sign calling for a cease-fire in the Hamas-Israel war on Nov. 21...

Associated Press

Hamas releases a third group of hostages as part of truce, and says it will seek to extend the deal

The fragile cease-fire between Israel and Hamas was back on track Sunday as the first American was released under a four-day truce.

8 days ago

Men look over the site of a deadly explosion at Al-Ahli Hospital in Gaza City, Wednesday, Oct. 18, ...

Associated Press

New AP analysis of last month’s deadly Gaza hospital explosion rules out widely cited video

The Associated Press is publishing an updated visual analysis of the deadly Oct. 17 explosion at Gaza's Al-Ahli Hospital.

11 days ago

Peggy Simpson holds a photograph of law enforcement carrying Lee Harvey Oswald's gun through a hall...

Associated Press

JFK assassination remembered 60 years later by surviving witnesses to history, including AP reporter

Peggy Simpson is among the last surviving witnesses who are sharing their stories as the nation marks the 60th anniversary.

11 days ago

Israeli Prime Minister Benjamin Netanyahu, chairs the weekly cabinet meeting in Jerusalem, Sunday, ...

Associated Press

Israeli Cabinet approves cease-fire with Hamas; deal includes release of 50 hostages

Israel’s Cabinet on Wednesday approved a cease-fire deal with the Hamas militant group that would bring a temporary halt to a devastating war.

12 days ago

Sponsored Articles

Follow @KTAR923...

The 2023 Diamondbacks are a good example to count on the underdog

The Arizona Diamondbacks made the World Series as a surprise. That they made the playoffs at all, got past the Milwaukee Brewers in the NL Wild Card round, swept the Los Angeles Dodgers in the NLDS and won two road games in Philadelphia to close out a full seven-game NLCS went against every expectation. Now, […]

...

Midwestern University

Midwestern University: innovating Arizona health care education

Midwestern University’s Glendale Campus near Loop 101 and 59th Avenue is an established leader in health care education and one of Arizona’s largest and most valuable health care resources.

...

SCHWARTZ LASER EYE CENTER

Key dates for Arizona sports fans to look forward to this fall

Fall brings new beginnings in different ways for Arizona’s professional sports teams like the Cardinals and Coyotes.

Dominion, AG reach proposed agreement in offshore wind case