AP

Virginia regulators OK Dominion’s planned offshore wind farm

Aug 5, 2022, 2:16 PM | Updated: 2:53 pm

RICHMOND, Va. (AP) — State regulators on Friday approved an application from Dominion Energy Virginia to build an enormous offshore wind farm off the coast of Virginia Beach and recover the cost from ratepayers.

No parties to the monthslong proceeding had opposed the approval of the project, which will help the utility boost the proportion of its generation that comes from renewable resources. But many had raised concerns about affordability and possible risks to the utility’s captive ratepayers.

In its Friday order, the State Corporation Commission noted that the 176-turbine Coastal Virginia Offshore Wind Project will likely be the single largest project in Dominion’s history and said that because of its size, complexity and location, it faces an array of challenges. The commission included in its order three “consumer protections,” including a performance standard.

The commission’s order also approved facilities that will connect the wind farm to the existing transmission system.

Robert Blue, Dominion Energy’s president and CEO, said in a statement that the company was pleased with the approval but was reviewing the specifics of the order, “particularly the performance requirement.”

The project, which will be located about 27 miles off the coast, has an expected capital cost of $9.8 billion and has drawn broad support from local officials, policymakers, business groups and trade unions, who say it will help fight climate change and create jobs. Backers quickly celebrated the commission’s decision.

“We applaud the SCC for greenlighting new offshore wind power in Virginia. As the largest offshore wind project in the country, this project is a critical piece of our clean energy transition because it complements solar by generating power at night when the sun isn’t shining,” Will Cleveland, a senior attorney for the Southern Environmental Law Center, said in a statement.

Regarding costs, the SCC order said that over the wind farm’s projected 35-year lifetime, including the construction and its 30-year projected useful life, a typical residential customer is expected to see an average monthly bill increase of $4.72, with a peak monthly bill increase of $14.22 in 2027.

“To be clear, total Project costs, including financing costs, less investment tax credits, are estimated to be approximately $21.5 billion on a Virginia-jurisdictional basis, assuming such costs are reasonable and prudent. And all of these costs … will find their way into ratepayers electric bills in some manner,” the order said.

Dominion said in a news release that because offshore wind turbines have no fuel costs, the project is expected to save Virginia customers more than $3 billion during its first 10 years of operation.

The consumer protections in the commission’s order include a requirement that Dominion file a notice within 30 calendar days if it finds that the total project costs are expected to exceed the current estimate or if the final turbine installation is expected to be delayed beyond Feb. 4, 2027. Annual filings will also have to address “any material changes” to the project and explain any cost overruns.

The SCC also ordered that beginning with the commercial operation and extending through the life of the project, customers will be “held harmless” for any shortfall in energy production below a certain threshold.

Such a performance standard will protect customers who are paying for the project “from also having to pay for replacement energy if the Project does not generate the amount of electricity upon which Dominion bases its request and its cost estimates,” the order said.

The order goes on to warn that the performance standard, however, will not protect customers from cost overruns, or if the project is abandoned.

Commissioner Judith Jagdmann emphasized in a concurring opinion that the project was “legislatively favored.”

The 2020 Virginia Clean Economy Act, a sweeping overhaul of the state’s energy policy enacted by Democrats, included a number of renewable energy mandates intended to help address the threats of climate change and paved the way for the project.

The General Assembly, Jagdmann wrote, could consider implementing additional consumer protections.

Friday’s decision came after months of voluminous filings in the case and a multiday evidentiary hearing in May.

The company already has a two-turbine pilot project up and running. The 2.6-gigawatt, utility-scale project’s schedule calls for construction to be complete in 2026. Dominion expects the project to generate enough clean energy to power up to 660,000 homes.

Copyright © The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

AP

FILE - Crystal Baziel holds the Pan-African flag Monday, June 19, 2023, during Reedy Chapel A.M.E C...

Associated Press

The beginner’s guide to celebrating Juneteenth

For more than one-and-a-half centuries, the Juneteenth holiday has been sacred to many Black communities. It marks the day in 1865 enslaved people in Galveston, Texas found out they had been freed — after the end of the Civil War, and two years after President Abraham Lincoln’s Emancipation Proclamation. Since it was designated a federal […]

4 hours ago

A Boeing 737 Max suffered damage to parts of the plane's structure after it went into a “Dutch ro...

Associated Press

Plane that did ‘Dutch roll’ on flight from Phoenix suffered structural damage, investigators say

A Boeing 737 Max suffered damage to parts of the plane's structure after it went into a “Dutch roll” during a flight from Phoenix last month.

5 days ago

This photo provided by Randy Shannon shows Mooney Falls on the Havasupai reservation outside the vi...

Associated Press

Dozens report illness after trips to waterfalls near Grand Canyon

Dozens of hikers say they fell ill during trips to a popular Arizona tourist destination that features towering blue-green waterfalls deep in a gorge neighboring Grand Canyon National Park.

6 days ago

Mugshot of Rudy Giuliani, who was processed Monday, June 10, 2024, in the Arizona fake electors cas...

Associated Press

Rudy Giuliani posts $10K cash bond after being processed in Arizona fake electors case

Rudy Giuliani, a former New York City mayor and Donald Trump attorney, was processed Monday in the Arizona fake electors case.

8 days ago

FILE - White House former chief of staff Mark Meadows speaks with reporters at the White House, Wed...

Associated Press

Former Trump chief of staff Mark Meadows pleads not guilty in Arizona fake elector case

Former Donald Trump presidential chief of staff Mark Meadows and Trump 2020 Election Day operations director Michael Roman pleaded not guilty Friday in Phoenix to nine felony charges for their roles in an effort to overturn Trump's Arizona election loss to Joe Biden.

12 days ago

deadly heat wave last summer...

Associated Press

After a deadly heat wave last summer, metro Phoenix is changing tactics

Fresh memories of the deadly heat wave last summer have led Arizona authorities to launch new tactics ahead of summer 2024.

22 days ago

Sponsored Articles

...

Sanderson Ford

3 new rides for 3 new road trips in Arizona

It's time for the Sanderson Ford Memorial Day sale with the Mighty Fine 69 Anniversary, as Sanderson Ford turned 69 years old in May.

...

DESERT INSTITUTE FOR SPINE CARE

Desert Institute for Spine Care is the place for weekend warriors to fix their back pain

Spring has sprung and nothing is better than March in Arizona. The temperatures are perfect and with the beautiful weather, Arizona has become a hotbed for hikers, runners, golfers, pickleball players and all types of weekend warriors.

...

DISC Desert Institute for Spine Care

Sciatica pain is treatable but surgery may be required

Sciatica pain is one of the most common ailments a person can face, and if not taken seriously, it could become one of the most harmful.

Virginia regulators OK Dominion’s planned offshore wind farm