Long Vt. bridge split to be widened for traffic

Jun 18, 2012, 9:51 PM

Associated Press

RICHMOND, Vt. (AP) – After more than a year of planning using computers, laser levels and measuring devices accurate to a fraction of a millimeter, it took engineers with tape measures and construction workers with sledgehammers to finally bring the 83-year-old Checkered House Bridge into the 21st century.

On Monday, workers cut the historic 350-foot U.S. Route 2 bridge in two lengthwise by unbolting the braces holding the trusses together and began the process of pushing the sides apart to widen the span by 12 1/2 feet.

As far as anyone involved in the project has been able to determine, it’s the first time such a technique has been tried on such a large bridge. Officials say the wider bridge is needed to accommodate modern traffic that frequently includes bicyclists, pedestrians and farm equipment. The span is scheduled to reopen a year from now.

Despite the preparations, the hardest push was the first. After workers moved one 300,000-pound truss about 2 inches downstream on the Winooski River on Monday, crews spent hours trying to free a single spot at the base of the bridge where, despite the specialized rollers it was laid on and pressure from hydraulic jacks, it remained stuck.

“I’m really not surprised. It’s such a large structure and such an old structure that there have to be points, friction points, that it hangs up on,” said Dale Gozalkowski, of the Albany, N.Y.-based engineer firm Clough Harbour & Associates, who helped design the project and watched Monday as it was put into action.

The original 350-foot Pennsylvania truss bridge was built in 1929, two years after an epic flood washed out a covered bridge in the same spot. The bridges are marked by the crisscrossing I-beams that form a latticework, creating a steel canopy above the road surface.

Vermont Transportation Agency officials have known for decades that the aging bridge about 10 miles east of Burlington needed to be upgraded or replaced. The travel surface was 20 feet wide, barely wide enough for two vehicles to pass each other, and the aging steel and the road surface was deteriorating.

For years, Vermont officials debated the best course of action. They considered tearing it down and building a new one, leaving it alone or turning it into a one-lane bridge and building another alongside it. But the bridge is the last of its kind in Vermont on a major roadway and, as such, is historically significant, said Scott Newman, the historic preservation officer for the Vermont Agency of Transportation.

The total project cost for the bridge and the approaches on both sides is about $16 million. A new open bridge could have been built for about $7 million. But the federal law required that the historic bridge be preserved, if possible, Newman said.

“Folks are always looking at the bottom line and I don’t blame them. We are very conscious of the bottom line,” Newman said. “These are truly unique circumstances where you have a big structure that is highly significant where we need to be in compliance with federal regulations.”

But Vermont Transportation Secretary Brian Searles said Monday that the price comparison didn’t take into account the design-build system used for the Checkered House Bridge.

“One cannot discount the engineering significance of what is being accomplished this week in Richmond,” Searles said. “It is a truly innovative undertaking that will preserve what is believed to be a valuable historic resource.”

Once the decision to preserve the bridge was made, it became an engineering challenge.

“This is not something you see in a textbook every day,” Jerry Pfunter, of the Tallahassee, Fla.,-based Finley Engineering Group, which was contracted for the actual widening of the bridge. “Typically, we start with a clean slate; we’ve got new members; we can build the traditional connections. Here we have a situation where we are partially taking apart connections.”

After the two sides were separated, workers used tape measures to note the progress.

At several points on the bridge, the workers reported by radio the progress of the separation in inches and fractions of inches. On one end of the bridge, an old-fashioned 4-foot level was clamped onto the side of the bridge to provide an instant readout of whether the bridge truss was perfectly vertical.

Later Monday, the truss had gotten stuck a second time, although the truss was completely separated, and it appeared doubtful that crews would be able to make the push in one day.

(Copyright 2012 The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.)

United States News

southern Arizona rancher George Alan Kelly...

Associated Press

Trial of a southern Arizona rancher charged in fatal shooting of unarmed migrant goes to the jury

Closing arguments were made against a southern Arizona rancher accused of shooting an undocumented migrant on his land to death on Thursday.

5 hours ago

Associated Press

Unfair labor complaint filed against Notre Dame over athletes

SOUTH BEND, Ind. (AP) — An unfair labor complaint was filed Thursday against the University of Notre Dame for classifying college athletes as “student-athletes.” The complaint was filed with the National Labor Relations Board by a California-based group calling itself the College Basketball Players Association. It said Notre Dame is engaging in unfair labor practices […]

5 hours ago

Associated Press

US deports about 50 Haitians to nation hit with gang violence, ending monthslong pause in flights

MIAMI (AP) — The Biden administration sent about 50 Haitians back to their country on Thursday, authorities said, marking the first deportation flight in several months to the Caribbean nation struggling with surging gang violence. The Homeland Security Department said in a statement that it “will continue to enforce U.S. laws and policy throughout the […]

6 hours ago

Donald Trump's hush money trial: 12 jurors selected...

Associated Press

Although 12 jurors were picked for Donald Trump’s hush money trial, selection of alternates is ongoing

A jury of 12 people was seated Thursday in former President Donald Trump's hush money trial. The proceedings are close to opening statements.

7 hours ago

Associated Press

Legislation allowing doctor-assisted suicide narrowly clears Delaware House, heads to state Senate

DOVER, Del. (AP) — A bill allowing doctor-assisted suicide in Delaware narrowly cleared the Democrat-led House on Thursday and now goes to the state Senate for consideration. The bill is the latest iteration of legislation that has been repeatedly introduced by Newark Democrat Paul Baumbach since 2015, and it is the only proposal to make […]

8 hours ago

Associated Press

California governor pledges state oversight for cities, counties lagging on solving homelessness

SAN FRANCISCO (AP) — Nearly $200 million in grant money will go to California cities and counties to move homeless people from encampments into housing, Gov. Gavin Newsom announced Thursday while also pledging increased oversight of efforts by local governments to reduce homelessness. The Democratic governor said he will move 22 state personnel from a […]

8 hours ago

Sponsored Articles

...

Condor Airlines

Condor Airlines can get you smoothly from Phoenix to Frankfurt on new A330-900neo airplane

Adventure Awaits! And there's no better way to experience the vacation of your dreams than traveling with Condor Airlines.

...

DISC Desert Institute for Spine Care

Sciatica pain is treatable but surgery may be required

Sciatica pain is one of the most common ailments a person can face, and if not taken seriously, it could become one of the most harmful.

...

Collins Comfort Masters

Here’s 1 way to ensure your family is drinking safe water

Water is maybe one of the most important resources in our lives, and especially if you have kids, you want them to have access to safe water.

Long Vt. bridge split to be widened for traffic