VA averts construction shutdown at troubled Denver hospital

May 21, 2015, 3:25 PM

FILE – In this April 15, 2015 file photo, work continues on the Veterans Affairs hospital in ...

FILE - In this April 15, 2015 file photo, work continues on the Veterans Affairs hospital in Aurora, Colo. House Speaker John Boehner of Ohio says the Department of Veterans Affairs is no better off a year after former VA Secretary Eric Shinseki resigned. Shinseki had stepped down amid a scandal over long wait times for veterans seeking health care and falsified records to cover up the delays. (AP Photo/David Zalubowski, File)

(AP Photo/David Zalubowski, File)

DENVER (AP) — The Veterans Affairs Department averted a costly construction shutdown at its half-finished hospital outside Denver on Thursday, but it still has to persuade an angry Congress to come up with hundreds of millions of dollars more to complete the troubled project.

A last-minute deal allows work to continue for three weeks while the VA tries to meet congressional demands for a scaled-back project that won’t raise the federal deficit or take services away from veterans elsewhere.

Congress also wants the VA to fire those responsible for the massive cost overruns in Denver and make major internal changes to avoid a repeat — perhaps turning over responsibility for major construction projects to the Army Corps of Engineers.

“America’s patience is running out,” House Veterans Affairs Committee Chairman Jeff Miller warned Thursday after the deal was reached.

The ambitious, 184-bed medical center under construction in suburban Aurora is a collection of a dozen large interconnected buildings that would replace an old and overcrowded facility operating in Denver.

The new hospital is now expected to cost $1.73 billion, nearly triple the estimate the VA gave last year.

The VA said it was days away from hitting the project’s spending limit, and that if Congress didn’t raise the cap by Sunday, construction would stop. Contractor Kiewit-Turner estimated it would add up to $200 million to the cost to wind down the work and then crank it up again.

The deal reached Thursday raises the spending cap by $100 million, to $900 million. It doesn’t give the VA any additional money but allows it to spend funds that it has on hand.

The House quickly approved the agreement. Senate approval was expected by Friday.

“I am greatly relieved that we will have more time to negotiate a longer-term deal for the Aurora VA hospital,” said Rep. Mike Coffman, a Republican whose district includes the new facility.

Democratic Sen. Michael Bennet said a shutdown would have been “the worst of all possible outcomes.”

“We will continue to push for a long-term plan that includes accountability to make sure a calamity like this does not happen again and that this hospital is complete on time and on budget,” Bennet said.

A shutdown appeared likely as late as Wednesday when House Speaker John Boehner said the funding cap wouldn’t be raised until the VA came up with a plan to fund the project through to completion and agreed to significant internal changes.

Boehner relented Thursday and the short-term deal went through, Coffman said.

The VA has said it needs another $830 million to finish the project as designed. Hoping to appease Congress, the department offered to indefinitely delay a nursing home and a post-traumatic stress disorder clinic planned for the campus, saving about $55 million.

The VA wants to finish the project with money siphoned from a $5 billion fund Congress set up to resolve an embarrassing national scandal, long wait times for veterans to get health care. Republicans and Democrats balked, saying the VA needed to come up with a different funding plan.

“Veterans elsewhere cannot be forced to sacrifice just because of the catastrophe here,” Sen. Richard Blumenthal, D-Conn., said during a Senate Veterans Affairs Committee hearing in Aurora last month.

Coffman suggested diverting the VA’s multimillion-dollar bonus budget to the Denver hospital. VA Deputy Secretary Sloan Gibson called that “a lousy idea.”

The reasons the hospital costs escalated so sharply have yet to be fully explained. The VA has said the plans weren’t complete when work began, and VA construction executives tried to switch to a different type of design-and-build process too late.

At least two internal VA investigations are underway, and the department says all the key executives on the project have been replaced — some were demoted or transferred, and another retired one day after investigators interviewed him under oath. But no one has been fired, angering many in Congress.

Veterans are worried and feel caught in the middle.

“I know the VA’s done a lot of bad things, and we’re outraged over that,” said Steven Rylant, president of the United Veterans Committee of Colorado, a coalition of veterans groups. “But making them accountable shouldn’t keep us from getting a new veterans hospital.”

___

Follow Dan Elliott at http://twitter.com/DanElliottAP

Copyright © The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.

Health

Phoenix Children's Avondale...

Colton Krolak

Phoenix Children’s to open Avondale campus, meeting needs of southwest Valley

Phoenix Children’s is opening an emergency department on July 26 at its Avondale campus to help fill the need for pediatric services in the rapidly expanding southwest Valley.

9 months ago

Phoenix mom who triggered Amber Alert found unconscious with baby, drugs by her side...

Serena O'Sullivan

Police: Phoenix mom who triggered Amber Alert found unconscious with baby, drugs by her side

A mom who took her baby from a Phoenix hospital and triggered an Amber Alert was found unconscious with the child and drugs, officials said.

9 months ago

urgent care honorhealth...

Stephen Gugliociello

HonorHealth to acquire 26 urgent care centers from FastMed

Healthcare system HonorHealth has purchased 26 urgent care centers in Arizona from FastMed, the company announced Tuesday.

9 months ago

Hiker in extreme heat...

Associated Press

How extreme heat takes a toll on the mind and body, according to experts

Extreme heat takes a toll. Heavy sweating, dizziness, muscle spasms and vomiting are just a few signs of heat exhaustion.

9 months ago

Food Bank Fridays campaign success 2023...

Serena O'Sullivan

Gaydos and Chad beat personal record in third year of Food Bank Fridays event

Each year, KTAR News 92.3 FM's Gaydos + Chad host their Food Bank Fridays campaign to provide free meals for people in need.

10 months ago

Surprise house fire...

Serena O'Sullivan

House fire in Surprise sends firefighter, 3 others to hospital

A Monday night house fire in Surprise, AZ sent four people to the hospital for fire-related injuries, including one firefighter.

10 months ago

Sponsored Articles

...

COLLINS COMFORT MASTERS

Here are 5 things Arizona residents need to know about their HVAC system

It's warming back up in the Valley, which means it's time to think about your air conditioning system's preparedness for summer.

...

DISC Desert Institute for Spine Care

Sciatica pain is treatable but surgery may be required

Sciatica pain is one of the most common ailments a person can face, and if not taken seriously, it could become one of the most harmful.

(KTAR News Graphic)...

Boys & Girls Clubs

KTAR launches online holiday auction benefitting Boys & Girls Clubs of the Valley

KTAR is teaming up with The Boys & Girls Clubs of the Valley for a holiday auction benefitting thousands of Valley kids.

VA averts construction shutdown at troubled Denver hospital