WAYNESBORO, Ga. (AP) – Southern Co. has had a simple message for the past few years: The effort to build the country’s first new nuclear power plant in a generation was on time and on budget. Now, that message is changing.

The $14 billion project to build two reactors at Plant Vogtle is trending hundreds of millions of dollars over budget and trailing more than a year behind schedule, according to a report from a state-hired construction watchdog. Now top-ranking utility executives are saying quality counts more than cost.

“I say this very carefully _ we manage it so we keep costs the best we can,” said Buzz Miller, executive vice president of nuclear development at Southern Co., who oversees the project. “But building it right’s priority one. The absolute capital number here is not what’s important. What’s important is the overall project, economic and value to the customers for the next 60 to 80 years.”

Until recently, more typical were statements like these from Southern Co. CEO Tom Fanning in a September 2011 speech: “We are on budget. We are on schedule. Heavy lifting to go, but we’ll be successful.”

In a move that raised eyebrows of project critics, the company recently said that a contingency fee of 20- to 25-percent was normal for a project of this size. It did not request a contingency fee when state regulators approved the project.

Much rides on the project. Industry officials ranging from Fanning to U.S. Energy Secretary Steven Chu acknowledge it’s a test for whether the nuclear industry can construct new plants without the chronic delays and cost overruns seen in the last round of construction decades ago.

“If this project goes forward and is built on-budget, on-time and on-schedule, that would be a very good thing,” Chu told reporters during a February visit to the site. “A lot of other companies will say, `OK. We now know we can do this and it would be a good investment.'”

The site swirls with activity, hosting more than 2,000 workers in rural Waynesboro. On Tuesday, craft laborers were welding together massive pieces of what will become a giant steel case containing the guts of the first new reactor. In a major step, the metal vessel that will hold the hot, radioactive nuclear fuel was being transported to the construction site. One of the world’s largest lift derricks, essentially a 560-foot crane, will hoist massive, pre-fabricated parts of the reactor into place.

That first reactor was supposed to be finished in April 2016, followed by the second reactor a year later. While the company has not formally changed those dates, it said completion of the first reactor has been pushed to November 2016. Under questioning, an executive said the timeline might stretch to early-to-mid 2017. Now a state monitor reports that first reactor will be finished no earlier than June 2017. He estimated the cost of a one-year delay as in the range of hundreds of millions of dollars.

Robert Baker, a former utility regulator, said he planned to ask Georgia’s Public Service Commission to adopt a plan that would trim the utility’s profits if the project comes in over budget. Because the monopoly is guaranteed a profit on every dollar it spends, Baker said it has a disincentive to control costs.

“There is now no way that this project can come in on-budget and on-time as has been stated repeatedly,” he said.

Several issues account for the delays. Southern Co. received its license to build from federal regulators months later than expected. The companies building the plant still have not agreed on an updated start-to-finish schedule.

Metal bars that will become part of the plant foundation were not installed exactly as required in plans, an error uncovered by federal inspectors. That required extra time and fixes. The Shaw Group Inc. in Lake Charles, La., experienced difficulty meeting stringent documentation and other quality rules required in the nuclear industry as it built parts for the facility.

Miller said Southern Co. knew that vendors might need to re-master nuclear norms since the industry had been dormant for years. He said the problems can be overcome.

“I think the big lesson and what we look at is you have to keep at it, keep at it, keep at it,” Miller said.

He said the utility would not speed up construction at the expense of safety and quality. While the two existing reactors at Plant Vogtle were finished behind schedule and over budget, many observers consider them a prudent investment. Building costs were high, but the maintenance and nuclear fuel costs proved relatively low and steady.

“We’re not going to plan on shortening the time schedule because getting it right is far more important,” Miller said. “Get it right. There will be noise on cost, noise on schedule. Get it right. Long after you and I are dead this thing is going to be cranking out power.”

___

Online:

Southern Co. Plant Vogtle:
http://www.southerncompany.com/nuclearenergy/vogtle.aspx

___

Follow Ray Henry on Twitter:
http://twitter.com/rhenryAP

(Copyright 2012 The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.)

United States News

Associated Press

Ex-Philadelphia police officer pleads guilty in shooting death of 12-year-old boy

PHILADELPHIA (AP) — A fired Philadelphia police officer pleaded guilty Friday to murder in the shooting of a fleeing 12-year-old boy, who prosecutors have said was on the ground and unarmed when the officer fired the fatal shot. Edsaul Mendoza also pleaded guilty to possession of an instrument of crime as part of a plea […]

1 hour ago

Associated Press

Video of 2 bear cubs pulled from trees prompts North Carolina wildlife investigation but no charges

ASHEVILLE, N.C. (AP) — A video of people pulling two bear cubs from a tree in North Carolina as one person posed for a photo with one of the wild animals prompted an investigation, but a state wildlife official said Friday that no charges will be filed. When North Carolina Wildlife Resources Commission staff responded […]

2 hours ago

Former President Donald Trump sits in a Manhattan Criminal Court on April 19, 2024. A full jury was...

Associated Press

Full jury of 12, with 6 alternates, seated for Donald Trump’s criminal trial

A full jury was seated Friday in Donald Trump’s hush money case, the first criminal trial for a former president in U.S. history.

2 hours ago

Associated Press

Attorneys argue that Florida law discriminates against Chinese nationals trying to buy homes

An attorney asked a federal appeals court on Friday to block a controversial Florida law signed last year that restricts Chinese citizens from buying real estate in much of the state, calling it discriminatory and a violation of the federal government’s supremacy in deciding foreign affairs. Attorney Ashley Gorski, representing four Chinese nationals who live […]

2 hours ago

Associated Press

A convicted rapist is charged with murder in the killing of a Connecticut visiting nurse

A convicted rapist was charged with murder and attempted sexual assault Friday in the killing of a visiting nurse at a Connecticut halfway house for sex offenders in October — a crime that spurred calls for better safety measures for home health care workers. Authorities added the charges against Michael Reese, 39, as he appeared […]

2 hours ago

Associated Press

Catholic priest resigns from Michigan church following protests over his criticism of a gay author

BEAL CITY, Mich. (AP) — A Catholic priest has resigned as pastor of a church in a small central Michigan community, the result of weeks of controversy following his publicly expressed regret that a gay author had read a book to preschool children. Gay rights activists and others have held regular protests outside St. Joseph […]

2 hours ago

Sponsored Articles

...

Condor Airlines

Condor Airlines can get you smoothly from Phoenix to Frankfurt on new A330-900neo airplane

Adventure Awaits! And there's no better way to experience the vacation of your dreams than traveling with Condor Airlines.

...

COLLINS COMFORT MASTERS

Here are 5 things Arizona residents need to know about their HVAC system

It's warming back up in the Valley, which means it's time to think about your air conditioning system's preparedness for summer.

...

Fiesta Bowl Foundation

The 51st annual Vrbo Fiesta Bowl Parade is excitingly upon us

The 51st annual Vrbo Fiesta Bowl Parade presented by Lerner & Rowe is upon us! The attraction honors Arizona and the history of the game.

Pressure on as Southern Co. builds nuclear plant