$12.3 billion Hanford plant sees new costs, delays

Jun 26, 2012, 11:06 PM

Associated Press

YAKIMA, Wash. (AP) – A new cost estimate and construction schedule for a massive waste plant being built at the nation’s most contaminated nuclear site will be delayed at least a year as workers try to resolve serious technical problems raised by whistleblowers about design and safety, the U.S. Department of Energy said Tuesday.

The announcement seemed certain to spark new fears about the long-term viability of the project that has already been the subject of numerous lawsuits and remains a top priority of Washington and Oregon despite its ballooning budget and delays.

The $12.3 billion waste treatment plant is currently scheduled to begin operating in 2019, under a consent decree with Washington state, the Environmental Protection Agency and the Energy Department. The plant, long considered the cornerstone of the cleanup at Hanford, is being built to convert highly radioactive and toxic waste into a stable glass form for permanent disposal underground.

However, several workers have raised concerns about safety, particularly about erosion and corrosion in tanks and piping inside the plant. The issues are significant because the problem areas are inside so-called black cells, where high radioactivity levels will make the areas inaccessible for maintenance and repairs after the plant begins operating.

The Energy Department and its contractor hired to build the plant, Bechtel National Inc., have been working to develop a new price tag and construction schedule for the plant in light of those problems. But the Energy Department announced in a conference call that the new estimates will be delayed at least a year as it embarks on additional tests to resolve the issues.

The tests are expected to cost tens of millions of dollars.

Information gained from those tests could provide a higher level of confidence that the plant can perform as originally conceived for its 40-year life, said Dave Huizenga, senior adviser for the agency’s Office of Environmental Management.

“We are committed to ultimately bringing this facility on line and having it operate in the long term in a safe and efficient manner,” he said.

Huizenga declined to speculate on how much more construction will cost or how long the plant will be delayed.

A massive undertaking, the plant will stand 12 stories tall and be the size of four football fields once completed. Design is 85 percent complete, and construction is more than 50 percent finished.

Washington Gov. Chris Gregoire, who has been outspoken about seeing the project completed, did not immediately comment on the announcement.

The federal government created Hanford in the 1940s as part of the top-secret project to build the atomic bomb. The site produced plutonium for the world’s first atomic blast and for the bomb that was dropped on Nagasaki, Japan, to end World War II.

Today, it is the nation’s most contaminated nuclear site, with cleanup expected to last decades.

Central to that cleanup is removing millions of gallons of highly toxic, radioactive stew _ enough to fill dozens of Olympic-size swimming pools _ from aging, underground tanks. Some of those tanks have leaked, threatening the groundwater and neighboring Columbia River.

Building a plant to convert that waste into a solid, stable form has been among the most challenging tasks at the site. The project has involved numerous technical problems, delays and cost increases. More recently, several workers raised safety concerns and two filed a lawsuit as whistleblowers, saying they were targeted for reprisals for raising questions.

In addition to erosion and corrosion, problems remain unresolved with adequate mixing of the waste.

“We’re all, frankly, disappointed that this waste stream is so complicated and it’s causing us these kind of issues and these kind of problems,” Huizenga said. “But I think we’re addressing these with a group of technical experts and our contractor. We’re trying to look for multiple different ways of solving the problems.”

The agency spends roughly one-third of its entire budget for nuclear cleanup _ about $2 billion each year _ at Hanford. Nearly a third of that goes to construction of the plant, the cost of which has grown from $4.3 billion to $12.3 billion.

Late last year, the Energy Department announced that the plant will cost as much as $900 million more and could take longer to build.

Then in March, the Defense Nuclear Facilities Safety Board ruled that the agency lacks necessary information to resolve some technical problems and establish a complete safety plan.

Tom Carpenter of Hanford Challenge, a group representing the whistleblowers, called Tuesday’s development “huge” and said he’s glad the Energy Department is paying attention to safety issues that are far more important than the cost and schedule.

“You just can’t help but wonder what took them so long,” he said.

Now, the Energy Department and its contractors must work to rebuild their credibility and salvage the project following months of friction, he said.

“This isn’t a situation where we’re trying to stop a facility. We want to see it proceed,” he said. “But we want it to proceed safely.”

(Copyright 2012 The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.)

United States News

southern Arizona rancher George Alan Kelly...

Associated Press

Trial of a southern Arizona rancher charged in fatal shooting of unarmed migrant goes to the jury

Closing arguments were made against a southern Arizona rancher accused of shooting an undocumented migrant on his land to death on Thursday.

10 hours ago

Associated Press

Unfair labor complaint filed against Notre Dame over athletes

SOUTH BEND, Ind. (AP) — An unfair labor complaint was filed Thursday against the University of Notre Dame for classifying college athletes as “student-athletes.” The complaint was filed with the National Labor Relations Board by a California-based group calling itself the College Basketball Players Association. It said Notre Dame is engaging in unfair labor practices […]

10 hours ago

Associated Press

US deports about 50 Haitians to nation hit with gang violence, ending monthslong pause in flights

MIAMI (AP) — The Biden administration sent about 50 Haitians back to their country on Thursday, authorities said, marking the first deportation flight in several months to the Caribbean nation struggling with surging gang violence. The Homeland Security Department said in a statement that it “will continue to enforce U.S. laws and policy throughout the […]

11 hours ago

Donald Trump's hush money trial: 12 jurors selected...

Associated Press

Although 12 jurors were picked for Donald Trump’s hush money trial, selection of alternates is ongoing

A jury of 12 people was seated Thursday in former President Donald Trump's hush money trial. The proceedings are close to opening statements.

12 hours ago

Associated Press

Legislation allowing doctor-assisted suicide narrowly clears Delaware House, heads to state Senate

DOVER, Del. (AP) — A bill allowing doctor-assisted suicide in Delaware narrowly cleared the Democrat-led House on Thursday and now goes to the state Senate for consideration. The bill is the latest iteration of legislation that has been repeatedly introduced by Newark Democrat Paul Baumbach since 2015, and it is the only proposal to make […]

13 hours ago

Associated Press

California governor pledges state oversight for cities, counties lagging on solving homelessness

SAN FRANCISCO (AP) — Nearly $200 million in grant money will go to California cities and counties to move homeless people from encampments into housing, Gov. Gavin Newsom announced Thursday while also pledging increased oversight of efforts by local governments to reduce homelessness. The Democratic governor said he will move 22 state personnel from a […]

13 hours ago

Sponsored Articles

...

COLLINS COMFORT MASTERS

Here are 5 things Arizona residents need to know about their HVAC system

It's warming back up in the Valley, which means it's time to think about your air conditioning system's preparedness for summer.

...

DISC Desert Institute for Spine Care

Sciatica pain is treatable but surgery may be required

Sciatica pain is one of the most common ailments a person can face, and if not taken seriously, it could become one of the most harmful.

...

Fiesta Bowl Foundation

The 51st annual Vrbo Fiesta Bowl Parade is excitingly upon us

The 51st annual Vrbo Fiesta Bowl Parade presented by Lerner & Rowe is upon us! The attraction honors Arizona and the history of the game.

$12.3 billion Hanford plant sees new costs, delays